From Monday, January 11, 2021, the Centre will begin major renovation work on its entrance hall. Work is scheduled to continue until early July. The work will be carried out in 10 successive, highly localized phases, to ensure continuity of circulation and access to services.
As the work progresses, we'll be presenting each new phase in this news blog, detailing its impact on the Center's users.
We hope that this work will cause as little inconvenience as possible. Thank you for your understanding.
A 10-phase project
The works involve the entire entrance hall, from the main entrance to the ambulance entrance, as well as the access corridor to the Oncology Day Hospital.
The waiting room at the entrances office is also concerned, for reasons of aesthetic coherence.

Provisional work schedule
Phase 1: January/February
Phase 2: February
Phase 3: late February/early March
Phase 4: March
Phase 5: late March/mid-April
Phase 6: mid-April / end of April
Phase 7: end of April / beginning of May
Phase 8: mid-May
Phase 9: end of May / beginning of June
Phase 10: June / beginning of July
Type of work
- Complete renovation of floors ;
- Change of reception desk and furniture;
- Renovation of lighting, paintwork and wall coverings;
- Creation of enclosed waiting areas;
- Security control panel ;
- Installation of new signage.
Details of Phase 1
Updated 01/27/2021
Entrance hall: Work until February 10, 2021

Accesses on the left-hand side of the entrance will be affected:
- Elevator parking lot: PRM access diverted through the ambulance hatch until January 27;
- Therapeutic garden: closed until January 27;
- Espace de Rencontres et d'Information (ERI): temporary office on the 6th floor (door no. 604) until February 1.
The ERI can still be contacted on 02 31 45 50 64 / eri@baclesse.unicancer.fr
Right-side access to the entrance will be affected from January 27, 5:30pm to February 10:
- Cafeteria: Access to vending machines only during cafeteria opening hours (during the health crisis: Monday to Friday, 9am to 4pm).