Phase 3 of the lobby renovation, which began on April 7, was completed on April 19. Work on phase 4 and phase 5 begins the next day along the cafeteria.
Consequences for users :
- Access to and from the cafeteria will be direct from the area near the vending machine. A pathway will be laid.
- Reception desk: the current reception desk will be removed to facilitate access to the hall, due to the size of the palisades. A temporary reception desk will be set up at the security control room.
- Estimated duration of work: 4 weeks, i.e. until May 14.